MiningMX
MiningMX

Endeavour flags weaker gold output on Mana shutdown

Ian Cockerill, CEO, Endeavour Mining
Ian Cockerill, CEO, Endeavour Mining

ENDEAVOUR Mining expects full-year gold production in the lower half of its target range following disruptions at its Mana mine in Burkina Faso, where underground mining and processing are not expected to resume until the second quarter of 2027.

The London-listed miner said on Thursday it remained on track to produce between 1.09 million and 1.265 million ounces (oz) this year. However, weaker-than-expected output at Mana would only be partly offset by stronger production at its Lafigué mine in Côte d’Ivoire.

Mana is now expected to miss the lower end of its own production target of 155,000 to 180,000 oz. All-in sustaining costs (AISC) will also exceed the upper end of its $2,000 to $2,250/oz forecast.

Burkina Faso regulations

Endeavour also faces new regulatory requirements in Burkina Faso, where the government has ordered that all gold doré produced in the country must be refined domestically from November 1.

Gold doré is a partially refined form of gold produced at mines before further processing at a refinery. Endeavour said it was in discussions with the local refinery over implementation at Mana and Houndé, its other mine in Burkina Faso.

The move forms part of Burkina Faso's efforts to tighten control over its gold industry. Bloomberg reported in September that the military-led government had opened the country's first gold refinery.

Cockerill has previously expressed confidence in Endeavour's operating environment in Burkina Faso, despite increased government intervention in the mining industry.

In July, he said conditions had become more stable and the authorities appeared to have greater control over the country. However, he acknowledged that new government requirements for the supply of mining materials had initially disrupted operations.

Mana disruption

Underground mining at Mana was suspended on October 28 after part of an access ramp subsided. The incident restricted access to two underground portals. Mining at a third portal was halted as a precaution.

Cockerill told analysts on Thursday that Mana had been a strong contributor to group cash flow before the incident. He described the disruption as an unfortunate setback and indicated that Endeavour remained confident about restoring underground operations.

"It is not going to be an overnight sort of turnaround story," he said.

Initial investigations suggest that weak rock associated with a geological shear zone collapsed into older underground workings. Cockerill said there had been no associated seismic activity and that investigations had found no further deterioration in the deeper workings.

The company is considering whether additional underground access routes will be required as part of the rehabilitation programme. Cockerill said more detailed plans would be available when Endeavour reports its year-end results in January.

The company now expects rehabilitation work to begin during the fourth quarter. Underground ore mining and processing are scheduled to resume in the second quarter of 2027.

Endeavour has also started discussions with Burkina Faso's Minister of Mines about the proposed restart. Cockerill said the authorities would participate in reviewing the rehabilitation plan and would have to approve the resumption of underground operations.

The company is accelerating open-pit development to supplement future underground production.

Endeavour had received the necessary permit for work at Bana Camp and expected to begin stripping early next year. Ore stockpiling could start during the second quarter.

Revised production, cost and capital expenditure forecasts for Mana in 2027 are expected in January.

Endeavour produced 256,000 oz in the September quarter, down 10% from the preceding quarter. Production for the first nine months fell 10% to 820,000 oz.

The company expects a stronger fourth quarter, supported by higher grades at its Houndé mine in Burkina Faso, Ity in Côte d’Ivoire and Sabodala-Massawa in Senegal.

Group AISC rose 37% year on year to $1,866/oz over the nine months, above its full-year target range of $1,600–$1,800/oz. Endeavour said higher gold prices added $166/oz to royalty costs. Adjusted AISC was therefore $1,700/oz, within the target range.

Despite lower production, higher gold prices lifted nine-month free cash flow 50% to a record $1.02bn.

Cockerill said stronger performance at Lafigué had largely offset the disruptions at Mana. The group therefore remained on track to meet its full-year targets.